Engine 93 Final Inspection Complete

Print this story (opens in a new tab)News RSS feed (opens in a new tab)Share on Facebook (opens in a new window)Share on X (opens in a new window)Add a comment

By Engine 93 Committee
October 15, 2010

Some of the Committee Members traveled back to Appleton, Wisconsin with our Dealer Randy Schwartz to complete the Final Inspection of Engine 93. The committee worked long hours going line item by line item and every little detail of the apparatus. After we were complete there were about 15 or so things that needed to be looked at or changed on the Engine. In the next few weeks it is expected to arrive at the Station where tool mounting and training will be done so that the Tanker can be placed in-service around the 1st of the Year.

Committee Members that completed the Inspection were:
Shawn Downs
Jeff Evans
Pat Stanley
Jim Foster
Les Hansen