Tower-9, Week 3 Progress Report for 6/3/16 |
By Deputy Fire Chief Steve Stockwell | |
June 3, 2016 | |
This is the weekly update for Tower-9, as you can see the cab moved up for wiring, lights, interior components, etc. while your aerial device was being prepped for paint. From what I heard, it passed testing with flying colors... not too shabby for 43 years young. Next week expect the cab to be completed, chassis to be complete or near complete for the frame-up/fabrication work and move to chassis line for drivetrain and body to begin fabrication. Sorry I have left out the Aerial Basket/Bucket as it is the wrong apparatus' bucket all together. Please stay tuned... |
|
Units: | TWR-9 |
Mutual Aid: | Pierce |